Gallery

Construction Updates

Excavation Work is in Progress
Nailing work is in progress
Contractor Mobilization – Site office, Cement store & D.G
Tower 1
Tower 2

Hero Homes Construction Updates July 2019

Excavation Work is in Progress

Contractor Mobilization – WTP, Batching Plant, Cement Store.

Nailing work is in progress


Hero Homes Construction Updates Oct. 2019

Tower 1 - Raft Completed Sear wall is in progress

Tower 2 - Raft in progress

Excavation Work is in Progress in T5, 6 & 7

Nailing /shotcrete work is in progress

Excavation Work is in Progress in
T5, 6 & 7

PCC & Water Proofing work is in progress in Tower and non-Tower Area.


Hero Homes Construction Updates Feb. 2020

Tower 1
Upper Basement Floor slab completed

Tower 2
Upper Basement Floor slab is in progress

Tower 3
LB level shear wall casting work is in progress

Tower 4
Raft casting work is in progress

Excavation Work is in Progress in T5, 6 & 7

Construction Updates of Hero Homes Sector 104 in Gurgaon

9718263263 Quick Enquiry